Location: UK
Customer: CVB JV
Working years: 2022 - 2023
Project information: The GRECT (Greenwich Connection Tunnel) is part of the Super Sewer Tideway tunnel project.
The tunnel, 4.5km long, will connect Greenwich Pumping Station to the main super sewer at Chambers Wharf providing additional sewer capacity in South East London and will help tackle the problem of sewage overflow into Deptford Creek, also known as the River Ravensbourne.
Supplied equipments: No.6 Fullround Formworks equipped with:
- Independent transport gantries
- Full setting automation
- K-ONE casting system
- VMT SPS Shutter Positioning System
Additional Services:
Machine installation , Machine Removal ,
Privacy
By using this site, you accept the use of our cookies. We use cookies to provide you with a better experience and to improve the performance of your site.